Facility upgrade to improve cooling tower operations. Our installation included conduit, wiring and electrical hookups to multiple electrical devices and apparatus. We installed 10 control […]
Installed 6ea. MPTS (Maximum Power Transfer Solutions) on selected loads. Improved Power Factor from .50 to .95 reducing carbon footprint and impact of greenhouse gases […]
Facility upgrade for new chemical process. Installation of conduit, wire, and electrical apparatus for hookup of valves, flow meters, temperature sensors, motors and other electrical […]
Facility upgrade of control and power systems for paper mill equipment. Installation included thousands of feet of conduit, wiring, and electrical apparatus for hookup of […]
Installation of VFDs and all maintenance on all existing VFDs, PLCs and SCADA system. Multi-site replacement of Scada System and ongoing maintenance and support across […]
Repair and replacement of existing VFD/Drives, Scada System and PLC Programming As the Operator in Charge of the Clinton Water Treatment facility I am pleased […]
Provided a state-of-the-art Arc Flash Study for compliance and provided on-site education to safety team. I want to thank you and your company for providing […]